Port Latta Offshore HV Cable

August, 2025

In 2023 Contact Group’s northern technicians completed a challenging and unique project at Port Latta in north-west Tasmania, for mining company Grange Resources.

Our highly skilled technicians were selected to carry out the replacement of the High Voltage offshore cable, which powers the processing plant’s 1-point-8-kilometre-long jetty and associated infrastructure.

Grange Resources processes iron ore from the company’s Savage River mine, which is pumped up as slurry and converted into iron ore pellets, then shipped out from the impressive looking jetty and wharf.

Contact Group’s HV Operations Supervisor, Stuart Styles, said it was a really interesting job, that required hours of research and preparation, with the project of critical importance to Grange.

“They had parallel 3.3 kilovolt feeders running offshore which I believe were close to 50 years old and continually failing, holding up ship loading operations,” he said.

The replacement cables were 2.25 kilometres long each, which proved a challenge to install.

Working with Grange engineers, Stuart said it was decided to carry out the installation in three cuts, two of them at 875 metres each and the final one at 500 metres.

Contact Group technicians installed them in succession, then joined them up and tested them.

But the work wasn’t straight forward.

“If we were going to do it with cable rollers like we normally would, we would need thousands of them and it just wasn’t financially viable, so we had to research other products and materials until we found something that did the job perfectly,” Stuart said.

“That took us three weeks to put down, but the product worked a treat and, in the end, we were winching about three metres of cable a minute,” he said.

Overall the installation went really well.

“We were able to pull in some favours from other industries to access specialist equipment, which was a game changer. The cable drums themselves weighed 3.5 tonnes, so we had to have a driven roller on shore and with that we managed to have the majority of the cables winched in in a couple of weeks,” Stuart said.

But the weather was a major challenge.

“The weather was a real unknown. Some days we were working a kilometre offshore halfway along the conveyor belt, and when Stanley disappeared under rain, we were 15 minutes away from shelter,” he said.

Luckily the team had access to one of the company’s specialist vehicles and trailers.

“It’s genius, they use ride-on lawn mowers without the cutter decks on them, but the western side of the jetty where all the services run is foot traffic only, so I think one day I clocked up about 27-kilometres of walking,” Stuart said.

He said most the technicians were doing 20 plus kms a day and deserved a big shoutout for all their hard work.

“They did a really good job, especially staying away from their young families for extended periods of time and working long hours when required.”

Stuart said they were all grateful for the opportunity though, given it’s the type of work we don’t get to do very often, something that’s quite unique.

“It was really rewarding to see the final results of such a long process, it was a high risk, high reward job, and to get feedback recently from Port Latta that their feed rates are up, was fantastic.”

He said they had five ships come in over the Christmas period and the cable didn’t miss a beat, so it’s been a great result for Grange.

“There’s massive financial implications if they’ve got a ship sitting out there that they can’t load, so this highlights that the project was a huge success, as stated in our feedback from Grange,” Stuart said.

This project won the 2023 Small Industrial Award at the NECA Tasmania Excellence Awards.